Project Title :
RAPID Package #4 – EPCC of ARU, SRU, SWS, LSSU & SSU – Piping field erection & mechanical erection
Scope :
field erection of mechanical & piping, piping erection 180K dia-inch field erection, 400 mechanical items with weightage 6500 tons, with heavy items about 140 tons covering rotating, static equipment, stack welding and installation
Contract Value :
RM114.4million
Duration :
July 2016 – Dec 2018
Client :
Petrofac